Indicator “Estimate to complete”
The Estimate to complete (Estimate to complete, short: EC) indicator indicates how many days it is likely to take to complete the activity or project if work continues at current levels of efficiency. The total duration is expressed in days.
Calculation formula:
Estimate to complete = duration of activity/ Schedule performance
Estimate to complete = duration of activity/ Schedule performance
Hint
If the earned value to the current point in time is 0, objectiF RPM also displays 0 for the Expected total duration indicator.
If the earned value to the current point in time is 0, objectiF RPM also displays 0 for the Expected total duration indicator.
You create the indicator in the dashboard
- within a group by clicking on the plus button, selecting Create new indicator and selecting Estimate to complete in the subsequent dialog under Indicator type